Factory Power Costs Rose 15% in Ohio. Data Centres Are Driving the Bill

Federal data show the average industrial electricity price in Ohio up about 15% in a year, well ahead of the national rise. Much of the increase traces to capacity charges inflated by data centre demand on the PJM grid, and a regulatory fix is not coming soon. Until it does, the controllable part of a plant's power bill is the part operations teams can actually see.

November 16, 2026·Operations Finance
Analogue ammeters and red and green digital meter displays with selector switches mounted on an orange industrial control panel

Key Takeaways

  • EIA data put Ohio's average industrial electricity price at 9.75 cents per kilowatthour in August 2026, up from 8.47 cents a year earlier, a rise of about 15% against roughly 7% nationally.
  • Capacity prices in the PJM grid region rose from $28.92 per megawatt-day in 2024 to $329.17, and PJM's independent market monitor names data centre load growth as the primary reason.
  • Capacity charges make up about 10% of a residential bill but can be up to three times that share for manufacturers; one Ohio brick maker saw its monthly charge rise from $1,600 to $12,000.
  • On October 9, FERC rejected most of PJM's plan for connecting data centres and other large loads, and Jefferies analysts said the ruling could mean higher capacity prices for longer.

For most plants, electricity has been a line in the budget that moves with the weather and the fuel markets. In the mid-Atlantic and Midwest it is now moving with something else: the queue of data centres connecting to the same grid. Manufacturers in Ohio and Pennsylvania sit in the same rate classes as those new loads, and they are paying for the capacity being built to serve them. Relief through regulation looks slow and uncertain. That leaves operations leaders with a narrower question they can actually answer: how much of the power they already buy is doing useful work?

The Numbers Behind the Bill

The Energy Information Administration's latest state price table, released on October 23, puts the average US industrial electricity price at 9.64 cents per kilowatthour in August 2026, against 8.98 cents in August 2025, an increase of about 7%. The rises in states served by PJM are steeper. Ohio's industrial price went from 8.47 to 9.75 cents, about 15%. Illinois rose from 10.18 to 11.33 cents, about 11%, and Pennsylvania from 9.66 to 10.47 cents, about 8%. The 2026 figures are preliminary, but the direction matches a longer trend.

Reuters reported in July that industrial electricity prices in the year to December 2025 rose 31% in Pennsylvania and 26% in Ohio, compared with 7% nationwide. It traced much of that to capacity charges, the fees that pay generators to be available at peak. By Reuters' calculation, PJM capacity prices rose from $28.92 per megawatt-day in 2024 to $329.17, an increase of 1,038%. Capacity charges typically account for about 10% of a residential bill, but can represent up to three times that share for manufacturers.

The plant-level examples are stark. Belden Brick, a 141-year-old Ohio manufacturer, saw its monthly capacity charge rise from $1,600 to $12,000 and its electricity costs climb 90% in a year. It raised brick prices 4% and profits still shrank. Plaskolite's capacity charges across its Pennsylvania and Ohio facilities rose to $1.2 million a year from $200,000 a year earlier. "Manufacturing goes as power goes," Brad Belden, the company's president, told Reuters.

Why the Fix Is Not Coming Quickly

A 24/7 Wall St. analysis published on November 12 cites PJM's independent market monitor saying that "data center load growth is the primary reason" for tight supply and high prices. PJM projects peak summer demand rising from 161,000 MW to 241,000 MW over 15 years. Because manufacturers share a rate class with data centres, the analysis notes, rules written for hyperscalers land on factories as well.

The regulatory route offers little near-term relief. On October 9, as Utility Dive reported, the Federal Energy Regulatory Commission rejected most of PJM's plan for connecting data centres and other large loads, including an interim service that would have let them connect without matching new capacity if they accepted curtailment. FERC approved PJM's large-load definition and registry but said states have "a crucial role to play." Jefferies analysts said the ruling could lead to higher capacity prices in PJM for longer. The 24/7 Wall St. analysis adds that FERC has proposed transmission charges for onsite generation, which would weaken the case for plants building their own power.

Demand is not easing either. The EIA's November Short-Term Energy Outlook, released on November 10, expects record generation in 2026, "driven by growing demand from the commercial sector," and continued growth in commercial and industrial demand in 2027.

What Plants Can Still Control

A plant cannot set the capacity price, but it can control how much power it draws, when it draws it and how much of it is wasted. That requires metering detailed enough to attribute consumption to lines, assets and shifts, rather than one monthly utility invoice. Many plants already collect some of this data in their control and SCADA systems without ever turning it into a cost figure that a supervisor can act on. Compressed air leaks, idle equipment left running between shifts and poorly sequenced start-ups all show up as kilowatthours long before they show up as variance in the monthly accounts.

The managers Reuters interviewed are already looking for options. "We're trying to be as creative as possible just to maintain competitiveness," said John Holeman, director of facilities and maintenance at Tosoh SMD. For most plants, the cheapest option is to use less of what they already pay for.

A Power Cost Playbook for Operations Leaders

Data centres did not ask factories to pay for their growth, and many manufacturers are lobbying hard against doing so. But the bills are arriving now, and the regulators are moving slowly. The plants that cope best will be the ones that know where every kilowatthour goes, and stop paying for the ones that do no work.